Back to blogSwitching

Move your clinic to new software in six weeks, with every record intact and every patient booked

By the wai teamOctober 15, 20268 min read

Reviewed by The Wellness Clinical Team, October 5, 2026

A clinic owner in fine knit standing alone at the tall window of a vast canal-house clinic in Amsterdam on go-live morning, a quiet smile of relief, the canal and gabled houses in soft light, oak floors and a sculptural lamp

Key points

Summary

Switch in six phases. Plan what moves and who owns it, export every record in a computable format and test it, set the retention period for the old data under your country's law, run both systems in parallel for two to four weeks, train staff and tell patients, then go live on a quiet day with the old system kept read-only.

Six weeks from the export request, the clinic runs on its new system with every record intact and every future booking in place. Clinicians find each past letter where they expect it, and the old system is retired on schedule.

See it in your clinicThirty minutes on your own patients and doctors.

Request a demo
6 years
minimum retention for HIPAA policies and required documentation 3
Indefinitely
how long the AMA says immunization records should be kept 2
21% to 15%
fall in no-shows with reminders, across 21 randomised studies 5

See your own services and diary set up on wai, with a sample of your exported records checked against the new record before anything goes live.

The clinic software switching checklist
PhaseStepOwnerDone when
1. PlanList every data type the old system holds and mark it move, keep read-only or archiveSwitch ownerInventory signed off by a clinician and the operations lead
1. PlanSet a go-live date at least six weeks out on a low-volume daySwitch ownerDate in every clinician's diary
1. PlanCheck the old contract for notice period, export terms and feesOperations leadNotice date and export cost known in writing
2. ExportRequest a full export of every patient, with the format documentedOperations leadSupplier confirms format and delivery date in writing
2. ExportConfirm the export is computable, not images of pagesSwitch ownerA sample opens as structured data
2. ExportTest twenty complex patients field by field in the new systemLead clinicianAll twenty match, or each gap has a fix
2. ExportStore the raw export files securely, separate from the importOperations leadLocation, access list and encryption recorded
3. RetainConfirm the retention periods that apply in your country and stateData protection leadWritten retention policy updated
3. RetainAgree read-only access to the old system or its export for that periodOperations leadAccess route and end date documented
4. ParallelMove future appointments and check each against the old diaryFront desk leadEvery future booking matches
4. ParallelReconcile deposits, invoices and memberships dailyOperations leadTotals agree for seven days in a row
5. Train and tellTrain each role on its own workflows with real patientsSwitch ownerEach person has completed a full task unaided
5. Train and tellTell patients twice, two weeks before and on the dayFront desk leadMessage sent with the new booking link
5. Train and tellTurn on reminders for every bookingFront desk leadTest patient receives a reminder
6. Go liveFreeze the old system and take a final exportOperations leadFinal export filed with the first
6. Go liveRun a fifteen minute review each day for five daysSwitch ownerIssue log empty or every issue owned
6. Go liveCheck the audit log exports from the new systemData protection leadExport opened and filed

Decide what moves, what stays and who owns it

Inventory what the old system holds, from demographics, notes, letters, results and prescriptions to consent forms, appointments, invoices, payments, memberships, message history and the audit log. Mark each one move, keep read-only, or archive.

Name one owner for the whole switch and one for each phase. Pick a go-live date at least six weeks out, on a low-volume day, away from the end of a billing month and from any clinician's leave.

Export everything, and prove the export works

Ask the old supplier in writing for a full export, its format and the delivery date. In the US, certified record systems must let a user create an export of all of a single patient's electronic health information, without developer help, and support an export of all the electronic health information for the whole patient population.1 The files must be electronic and in a computable format, and a PDF counts only if it is machine-readable.1

Pick twenty patients with long histories, including children, a deceased patient and someone with a complex medication list, and check each one field by field in the new system. Keep the raw export files as well as the imported version as the clinic's evidence of what the old record said. For scribe notes, follow switching an AI scribe without losing records.

Retention rules outlive the old contract

Confirm your own retention periods before you cancel anything. In the US, HIPAA requires required policies and documentation to be kept for 6 years from creation or from when they were last in effect, whichever is later.3 The AMA's Code of Medical Ethics adds that physicians should keep what a new physician would reasonably need, keep immunization records indefinitely, and tell patients how to reach stored records and for how long they will be available.2

In the UK, the ICO's storage limitation principle says personal data must not be kept longer than needed, that the clinic must be able to justify how long it keeps it, and that it needs a policy with standard retention periods.4 Write or update that policy now, and record where the archived export is held and who can open it.

Run both systems in parallel

For two to four weeks, book new appointments in the new system and keep the old one open read-only for history. Move future appointments in one batch, then check every one against the old diary. Any clinician should be able to find a past letter in under a minute.

Reconcile money daily. Compare deposits, open invoices and memberships in both systems each evening until totals agree for a full week.

Train the team and tell the patients

Train each role on its own day with real patients. The front desk learns the inbox, booking and payments, and clinicians learn notes, letters and signing.

Tell patients two weeks before go-live and again on the day, with the new booking link, any new way to pay and confirmation that their record has moved with them. Switch reminders on for every booking from the first day. In a BMJ Open meta-analysis of 21 randomised studies, patients sent reminders were 23% more likely to attend and no-shows fell from 21% to 15%.5

Go live, then keep the old system read-only

On go-live day, stop new entries in the old system, take a final export and file it with the first. Hold a fifteen minute review at the end of each of the first five days and log every issue with an owner.

On wai, every message, draft, approval and signature is written to an event log the clinic can export, and signed notes and letters can be exported into other systems, so the clinic can always read its own history.76

wai hosts each clinic's records in its own country, under that country's rules. We set this up with your clinic. Booking reads each clinician's busy times from Google Calendar, Outlook or Apple Calendar so patients are only offered open times, and it never writes into a clinician's own calendar.

Where to start

This week, request the full export and its format from the current supplier in writing, and write down the retention periods that apply to your clinic. Then set the go-live date, name the owners and book the twenty-patient test. The implementation plan covers what comes after go-live, and wai prices are published on the pricing page.

Bring a sample export from your current system. We show you how it lands on wai, patient by patient, before you commit.

Frequently asked questions

How long does it take to switch clinic software?

Plan for about six weeks from the export request to go-live, including two to four weeks of parallel running. Most of the time goes on the export and the twenty-patient test.

How long must we keep the old records?

As long as the longest rule that applies to your clinic. HIPAA documentation must be kept for 6 years, and the AMA says immunization records should be kept indefinitely.32 Check your national and state rules and write them into your retention policy.4

Can the old supplier refuse to give us our data?

In the US, certified record systems must support a full export of every patient's electronic health information.1 Elsewhere, check the contract's export terms before giving notice, and ask for the format in writing.

Should we keep the old system after go-live?

Keep read-only access or a complete, tested export for the full retention period, with a documented way to open it, so every records request can be answered.

What should we tell patients?

That their record has moved with them, the new booking link, any new way to pay, and who to contact with questions. Send it two weeks before go-live and again on the day.

Can we take our records out of wai if we ever leave?

Yes. Signed notes and letters can be exported into other systems, and the event log can be exported too.67

Sources

  1. 1Assistant Secretary for Technology Policy and Office of the National Coordinator for Health IT, US HHS, 2026Electronic health information export, 45 CFR 170.315(b)(10) test methodRead 14 October 2026Read source
  2. 2American Medical AssociationCode of Medical Ethics Opinion 3.3.1, Management of medical recordsRead 14 October 2026Read source
  3. 3US Code of Federal Regulations (eCFR), 202645 CFR 164.316, policies and procedures and documentation requirementsRead 14 October 2026Read source
  4. 4Information Commissioner's OfficePrinciple (e), storage limitationRead 14 October 2026Read source
  5. 5BMJ Open, Robotham and colleagues, 2016Using digital notifications to improve attendance in clinic, systematic review and meta-analysisRead 14 October 2026Read source
  6. 6wai, 2026IntegrationsRead 14 October 2026Read source
  7. 7wai, 2026Security at waiRead 14 October 2026Read source
ShareLinkedInXWhatsApp

Your whole clinic on the new system, with every record and booking in place

Fifteen minutes with a clinician who uses wai every day, on your own diary and a sample of your records. We reply within one working day.

Your details are processed under our Privacy Policy and used to arrange the demo.

Partner with us

See it on your own patients, then build it with us

Thirty minutes on your own patients, doctors and rules, in your market. We reply within one working day, and the clinics that partner with us early shape what we build next.

See what wai does between the visits

See your clinic at its best.

Thirty minutes and you will see the consult, the front desk and the patient record working as one.

Request a demo